Please find below the projected timeline for the remainder of the Front/South Street Water Main Replacement Project:

  • Week of July 1, 2024: Replace water line services to the remainder of Front Street.
  • Week of July 8, 2024: Install temporary water main line on Front Street or Second Street and loam/seed affected lawns on South Street.
  • Week of July 15, 2024: Begin water main installation on Second Street or Front Street.
  • August: Install temporary water main line on Front Street or Second Street and loam/seed affected lawns on Front Street or Second Street.
  • August: Begin water main installation on Second Street or Front Street.
  • September: Begin water main installation on Cross Street and loam/seed affected lawns on Front Street or Second Street.
  • Early to Mid-Fall: Temporary paving performed by Rollinsford DPW. This also includes affected areas of driveways.

Please find below other notes regarding this project:

  • Currently, a police detail will be on site for the work on Front Street.
  • Removed trees will be replaced.
  • Roads will not be closed to residents.
  • On Second Street, the Town is also planning to replace some drainage in tandem with this project.